MEB was approached by Berkeley Eastern Counties to upgrade the district heat network for 195 Apartment over 5 blocks and refurbishment works to 10 large townhouses.

Project Overview At A Glance

  • Modifications to BMS Systems
  • Modifications to Secondary Pipework
  • Modifications of existing Energy Center
  • Replacement of existing HIU’s in occupied properties
  • Fire Stopping Inspection and Installation
  • Flushing, Balancing & Commissioning
  • Installation of new Underfloor Heating to Townhouses
  • Installation of new mechanical heat recovery ventilation to Townhouses
  • Removal of all finishes, fittings, luminaires, sanitaryware and reinstatement upon refurbishment to the Townhouses